A roadshow gets specified in the first venue. Somebody walks the room, agrees a screen size and a stage, and the drawing goes out to everybody. Then the third stop has a goods lift barely a metre wide, and the screen that worked twice has to be rebuilt smaller for the rest of the tour.
Audio visual, or AV, is the screens and the sound. Lighting and staging travel beside it and get specified the same way. Roadshow AV requirements are not one event’s requirements repeated at every stop. They are the set of things that have to work in every room on the schedule, which means they are decided by the most awkward room on it.
In short
- Specify the touring kit against the tightest opening and smallest lift anywhere on the schedule, not against the first venue you walked.
- A venue’s published specification may answer only half the question, so somebody has to chase the other half venue by venue.
- The drive legs set the shape of the tour, because drivers’ hours limit how long a driver can keep going.
- Two sets of kit leapfrogging is a specification decision, not a logistics afterthought.
Roadshow AV requirements are decided by the smallest venue
One set of equipment cannot be specified separately for each room. Whatever tours has to get through the narrowest opening and stand under the lowest ceiling anywhere on the schedule, because the alternative is rebuilding it halfway through the tour.
The screen is where that bites. Content is built to a fixed canvas, the exact dimensions the graphics are made to, so a screen that shrinks at stop three means the content gets made again, and the version the client signed off is not the version the audience sees. Staging goes the same way: a stage height that works on a flat floor becomes a clearance problem in a room with a lower ceiling.
We cover the single-room version of this in our post on product launch AV requirements, where the narrowest opening on the route in is the real constraint. A tour has several routes in, and each one needs its own check.
Two venues, two different halves of the answer
The two specifications below, from The Lowry and the Business Design Centre, answer different halves of the same question.
The Lowry’s technical specification for its Quays Theatre publishes dock doors of 6.3 metres wide by 3.1 metres high, and a goods lift 2.5 metres wide, 4.0 metres long and 3.0 metres high, with an exit door on the Quays dock side of 2.4 by 2.4 metres. More useful than any dimension: trucks load through that lift or into a scene dock to the rear of the Lyric stage, and access that way depends on whether the show in that space allows it. Somebody else’s show can close the route.
The Business Design Centre publishes height restrictions instead: 4.9 metres at the Liverpool Road entrance, 4.2 metres at the Barford Street exit, 4.0 metres in the upper loading bay and 3.0 metres in the lower one, plus two goods lifts, the Main Hall’s at 3.9 metres long by 1.9 wide by 1.9 high and the Gallery Hall’s at 5.5 metres long by 2.55 wide by 2.5 high, both taking 3,000 kilograms. It says there are doorways between the lifts and the halls, and does not give their sizes.
Neither document is a complete brief. The Lowry gives no vehicle weight or length limit, and the Business Design Centre gives no vehicle length limit and no door sizes. That is the work: ask each venue for the part it has not written down, before the kit list closes. Our post on the AV brief for an event covers what that information has to contain.
The schedule is a driving problem before it is a crew problem
A roadshow schedule can get built backwards from the room bookings, with the movement of the kit worked out afterwards. That order is where the trouble starts.
For a vehicle over 3.5 tonnes, GOV.UK’s guidance on drivers’ hours sets the assimilated rules at 9 hours of driving in a day, extendable to 10 hours twice a week, with a break or breaks totalling at least 45 minutes after no more than 4 hours 30 minutes of driving, and 56 hours in a week.
The drive has to fit inside those limits, and so do the hours around it. A de-rig, which is taking the whole build back down, can overrun, and a driver who has already done a long leg has no hours left to absorb it. A tour that looks tight on a spreadsheet can be impossible, and that is a conversation for weeks before the first venue.
One set of kit, or two
When the gap between two stops is shorter than de-rig plus drive plus build, one set of equipment cannot do it. Two sets leapfrog: the second room is being built while the first is still being struck.
That belongs in the first conversation, because it changes the kit list, the crew plan and the vehicle plan at once. What decides it is the gap between stops, the distance, how long each build honestly takes, and whether a venue gives overnight access or hands the room over at eight in the morning.
Splitting the work shows up here too. We hold that one supplier beats three, because dividing screens, lighting and staging between separate companies moves the coordination risk onto the client. On a single event that is one awkward handover. On a six-venue roadshow it is six, with nobody owning the fact that the lights arrived before the frame they hang from.
What actually tours is the show file
The equipment is the visible half. What keeps a roadshow consistent is the show file: the content canvas, the lighting states, the audio presets and the patch list, which records which cable feeds which channel.
Fix the canvas once, to the screen that works in every room, and the content survives the tour. Let it change at stop three and somebody is rebuilding graphics in a hotel. We wrote about building slides for a screen that is not 16:9, the standard widescreen shape, for the same reason: the canvas is a specification, not a preference.
Patch the same way in every venue too. Channel one stays channel one for the whole tour, cases are labelled for the position they go to rather than the kit inside them, and a technician who was not at yesterday’s build can still find the lectern feed. We go further into that in our post on long term AV hire.
Frequently asked questions
Do we need the same AV at every venue on the roadshow?
You need the same specification, not the same room. The screen size, the content canvas and the audio presets should hold across the tour, because changing them means remaking content and reprogramming. What changes venue by venue is how the kit gets in and where it hangs or stands, which is why each venue needs its own access check against one fixed kit list.
How long should we leave between roadshow venues?
Leave enough time for the de-rig, the drive and the next build, and measure the drive against drivers’ hours rather than a mapping app. For a vehicle over 3.5 tonnes, GOV.UK sets the daily driving limit under the assimilated rules at 9 hours, extendable to 10 twice a week, with a break or breaks totalling at least 45 minutes after no more than 4 hours 30 minutes. If the gap is shorter than de-rig, drive and build together, two sets of equipment beat a tighter schedule.
Sources
- The Lowry · Quays Theatre technical specification
- Business Design Centre · loading bay information
- GOV.UK · Drivers’ hours, assimilated rules
Talk to us about your roadshow
If you are planning a roadshow and want the kit specified once, send us four things: the type of event, the dates, the venues on the schedule and the audience size at each one. That is enough to tell you whether one set of equipment covers it or whether the gaps need two, and to quote for the whole tour. We deliver nationwide, with phone lines for national, London, Liverpool and Manchester. Send the detail through our contact page or email hire@eventproductiongroup.co.uk.