A stand at a trade show is the only room you will ever build where the people next door can ruin it. Your screen competes with theirs and your sound lands in their meeting. Two documents already say what you may and may not do about that, and exhibition stand AV requirements are set by those documents and the deadlines inside them, long before anyone picks an equipment list.

In short

  • Your audio visual (AV) choices on a stand are shaped by two things you do not control: the venue’s published guidance and your show’s own exhibitor manual.
  • Specialist 24 hour electrical supplies have to be requested 28 days before build up, the period when stands go in. Complex structures run to their own 28 day deadline.
  • At Aftermarket 2024 the rule was sound below 80 decibels, monitored, with loudspeakers facing inwards rather than at the gangways. Check what your show’s manual asks.
  • Decide what the stand has to achieve, then specify the kit. The other way round means finding the deadlines after the equipment is chosen.

What exhibition stand AV requirements actually depend on

The first document is the eGuide, published by the Association of Event Venues (AEV) and written for UK event venues. The AEV describes it as having “status similar to that of an approved code of practice”. The second is the exhibitor manual for your specific show, which comes from the organiser and carries that show’s own rules.

Neither is written for someone choosing a screen. Both decide what you are allowed to choose. The useful move is to read the AV-relevant parts of both before the equipment conversation, because the eGuide sets 28 day deadlines for power and for complex structures, and a deadline you have already missed is not a negotiation.

Power: the request that goes in 28 days early

If anything on your stand has to stay live after the hall closes, a screen looping content overnight or a chilled product display, that is a specialist 24 hour request rather than a standard supply. The eGuide’s electrical sub-section states that requests for specialist 24 hour supplies “must be presented to the venue no later than 28 days prior to the exhibition build up”, and that 24 hour supplies “cannot be guaranteed during build-up”.

Two more lines in the same sub-section matter for your stand. Once the installation is complete, the electrician must carry out a visual inspection followed by tests, and the test form goes to the venue before your supply is connected. And the equipment you carry in is yours to vouch for: “It is the owner or user’s responsibility to ensure that portable appliances are safe to be plugged into the electrical system.”

Sound: the rule your show sets

The exhibitor manual for Aftermarket 2024 at Farnborough International is specific about both halves of this: “sound must be kept to a level below 80 decibels. This level will be monitored”, and “All audio speakers must be facing inwards on the stand and not facing the gangways.”

That second sentence decides where your loudspeakers can point. A pair of loudspeakers at the front of the stand, aimed out at the gangway, is a public address (PA) system pointed at your neighbours. What sits comfortably inside a rule like that is near-field audio: small loudspeakers close to the screen and angled down into the stand. Where a demonstration needs more, headphones take it off the hall floor altogether.

In the eGuide, predicted noise levels are a required item in the method statement template for double decker stands, a method statement being the document setting out how work will be done. We have met the neighbouring-stand problem from the lighting side. On the MLE fashion show and lifestyle exhibition at Event City, our lighting designers faced the challenge of creating a maximum atmosphere around the catwalk without impacting the nearby exhibitor stands.

Screens: hanging one is a different job from standing one up

A screen on a floor stand or built into the stand frame is an ordinary hire. Hanging a light emitting diode (LED) wall from a truss, the metal framework that carries lights and screens, is a different conversation, because of what the eGuide calls a complex structure.

The stand build sub-section defines that as including “Any structure, regardless of its height, which requires structural calculations”, along with multi-storey stands, and states that “Organisers are responsible for submitting full details of all complex structures no later than 28 days prior to tenancy”, tenancy being the period the organiser holds the hall. Separately, the Farnborough 2024 manual asks exhibitors planning displays 4 metres high or above to contact the organisers.

Rigging, the work of suspending equipment overhead, is a scheduled activity on site. The eGuide describes agreeing a rigging schedule covering cherry picker or hoist access, with a banksman provided and the working area cordoned off, a banksman being the person who directs the machine and keeps people clear of it. The floor-standing alternative exists: on the MLE exhibition we housed the catwalk lighting on a large freestanding truss structure.

What to settle before you order the equipment

Six answers cover almost everything, and all six belong in the brief rather than in a conversation during build up.

  • Which show and which hall, and the current version of that show’s exhibitor manual.
  • Whether anything has to stay live overnight, because that request goes in 28 days ahead.
  • Who is wiring the stand, and which electrician issues the test form the venue needs.
  • The sound limit your manual sets, and whether the demonstration you have planned works inside it.
  • Whether anything needs structural calculations, since the organiser has to submit those details 28 days before tenancy.
  • How deep the stand is, because viewing distance shapes the screen size before any specification does.

This is also the clearest argument we know for not splitting a stand across suppliers. Sound, screens and lighting bought from three companies means three sets of assumptions about which of those deadlines somebody else is meeting, and the coordination risk lands on you rather than on a supplier. We supply audio, video, lighting, rigging and staging from one source, which removes not one deadline. It does mean there is one company to ask. The same information belongs in the brief you send your supplier, and if your content has to fit an unusual screen shape, we have written separately about designing slides for a screen that is not 16:9.

Frequently asked questions

Do we need a 24 hour electrical supply on our stand?

Only if something has to run while the hall is closed. A screen you switch off at night and a laptop both sit on a standard supply. Looping content overnight or a refrigerated display needs the specialist 24 hour order, and the eGuide asks for that request 28 days before build up, so it is a decision you make early rather than on arrival.

Can we run sound on a stand without upsetting our neighbours?

You have two things to satisfy, and they are separate. Your show’s manual will set a level: at Aftermarket 2024 that was below 80 decibels, monitored. It can also set a direction, in that case loudspeakers facing inwards and not at the gangways. Keeping the level down is what meets the first. Moving the loudspeakers close to the screen and angling them into your space is what meets the second.

Sources

If you are exhibiting this season and would rather have the AV specified around your show’s rules than against them, tell us four things: what the event is, the dates, the venue and hall, and how many people you expect through the stand. That is enough for us to come back with a kit list and a quote. We supply AV for exhibitions from one source and deliver nationwide from Manchester. You can reach us through the contact page or by email at hire@eventproductiongroup.co.uk, and if your stand does not need any of this, we will say so.